Details of Aluminum Formwork (Mivan / MFE)
The
most effective means available for the construction of high, medium
and low rise mass housing R/C structures.
It
is a precision-engineered formwork fabricated in Aluminium.
Monolithic
pouring. Walls, columns, slabs & beam are poured together.
Speed
- Induces a disciplined & systemized approach to construction,
which creates a daily work cycle, the essence of the productivity.
The productivity generates a overall work cycle, that can achieve 4/5
day per floor outputs or other cycle times to suit your project
requirements.
It
is flexible in design and can form any architectural or structural
configuration, such as stairs, bay windows, curved features, etc.
Quality
- When struck the aluminium formwork reveals a good quality fair face
onto which a 4–5mm skim coat can be applied for a perfect finish
eliminating need of plaster.
Provides
an Integrated Scaffolding reducing the cost of your scaffolding
requirements.
Ease
of handling - The formwork panels are manually handled, generating
further savings on heavy equipment and cranage.
Mechanical
and electrical installation is simplified where conducts are embedded
in the structure and by precise engineering of outlets and service
ducts.
Cost
Analysis:
Range
is 155 US$ per m2 to 225 US$ per m2, most common being 160 US$ per m2
& assumed for cost comparison purpose.
Cost
of Aluminum Formwork is 160 US $ per sqm.
Consider
65.00 Rs/US$. Add 25.0 % duties (+ Octroi/Entry Tax/Local Body Tax)
So
Total Cost will be app 13,000 Rs/sqm. (160 X 65 X 1.25)
Your
project offers 100 uses (for 10 blocks of 10 storey)
Final
cost per sqm on item rate basis will be 130 Rs per sqm. ( Rs
13000 Formwork Cost/100 Uses) Depending on quality, traditional
formwork (Plywood & Batten) costs between 80 & 150 Rs/sqm
To
Workout Built up Area cost :-
For
Col-beam-slab structure with simple elevation:
Ratio
of Formwork Area to Builtup Area, on thumbrule base will be
approximately 3 (It may be as high as 4.5 if elevation is features
has double wall, double chhajja etc)
So
Cost of Mivan Formwork per sft of builtup Area will be (3 X
13000/10.76) =3625 (One time Cost)
For
100 uses it will be 3625/ 100 = 36.25 Rs/sft of builtup area.
For
Wall-slab structure with simple elevation:
Ratio
of Formwork Area to Builtup Area, on thumbrule base will be
approximately 5.5 (It may be as high as 7 if elevation is features
has double wall, double chhajja, etc. Or low cost project where room
dimensions are very small)
So
Cost of Mivan Formwork per sft of builtup Area will be (5.5 X
13000/10.76) =6645 (One time Cost)
For
100 uses it will be 6645/ 100 = 66.45 Rs/sft of builtup area.
Construction
period in above example:
1st
Tower
1st
slab
– 21 days
2nd
slab
– 18 days
3rd
slab
– 15 days
4th
slab
– 12 days
5th
slab
– 9 days
6th
to
25th
slab
– 140 days (@ 7 days per floor)
Total
– 205 days = 7.88 months considering 26 working days per month.
Next
each tower (25 slabs) – 175 days = 6.73 months considering 26
working days per month.
Total
Period – 7.88 months for 1st
tower
+ 3 X 6.73 months for subsequent towers
=
28.07 months, say 28 months.
Add
about 4 months as time to reach typical floor of 1st
tower
& 6 months for finishing after last floor of 4th
tower.
Total
construction period will be about 38 months.
Conventionally,
for 25 storey building, RCC will take about 2 years for including
foundation & 12 months for finishing. That is 36 months. This
means even after constructing one block at a time, total construction
period is almost same as constructing all 4 towers simultaneously
with traditional formwork.
Comments
I am a student of Advanced Construction Management from India, and would like to know more about how you derived these calculations for aluminium shuttering.
-Priya Raj, India
priyaaa15@gmail.com
The actual material cost is considered from mivan material supplying co & also based on practical experience (1 of my projects)
Rgds
Ram
Dear Priya
100% of built up area
30% of BUP area For walls i.e Twice for both side.
5% of BUP Area for Sills, Lintels.
Sum Up all Factors you get the ratio.
Initial Cost of Rs 1300/- per sft. is very high for residential buildings even if towers are 30 storied. It can only be useful if residential complex is spread over 60 acres and above.
Hello,
We have gone through your site Mivan Shuttering Details. We are impressed & eager to use it in our next project which is at Nagpur, Maharashtra, India....
Please send the details of Mivan shuttering in per square feet super built up area for G+10 storied (12 buildings) with 15 Acres Land..
Thank You
Our Contact details are as follows:--
Email Id:- giplnagpur@gmail.com
My building is going for redevelopment, a very small plot and a project of 7 storey building. Can i ask my builder for mivan technology. Will it be too expensive for him?
My building is going for redevelopment, a very small plot and a project of 7 storey building. Can i ask my builder for mivan technology. Will it be too expensive for him?
Aluminium shuttering cleaning solution to removing rust and concrete build-up on aluminium or mivan formwork. Aluminium shuttering cleaner quickly removes hardened concrete. Aluminium shuttering cleaner saving labour time in grinding and cleaning. The oxidation and corrosion of aluminium plate will not occur by using our chemical.
U r asking about builtup rate per sq.ft. am I rate sir.buitup labour rate in mivan us about 190 /- per sq.ft. if company provides mivan material
2. It gives smooth surface and hence do not require plaster. It also reduces an time and the water which is a considerable amount.
BeSealed® is the product range of Bekina® Compounds, a renown Belgian rubber compounder. Bekina® Compounds has been producing Bentobar+, a bentonite waterstop for the construction industry, for over 25 years now. Because of the big demand of our waterstops, Bekina® Compounds decided to launch its own waterstop brand: BeSealed®
At this moment BeSealed® is being sold in 35 countries and this number is still growing
BeSealed® offer three different Product range
# Water Swellable Formwork products
# Swellable Sealing Bars
# Sealing Inserts for Tunneling
We attach here with detail Introductory letter , Brochure for your kind perusal and record.
Check out “BeSealed®, active sealing solutions” from BeSealed® on Vimeo.
The video is available for your viewing pleasure at https://vimeo.com/153339100
Please do contact us if you have any further questions.
1. Always use safety goggles, rubber gloves, shoes before handling this chemical.
2. Area of operation should be open & airy with good air circulation.
3. Deep aluminium shuttering piece.
4. Solution level should be 10 cm above the top aluminium shuttering piece.
5. Wait for 5 minutes.
6. Rinse with water & dry.
7. Dispose off solution after neutralizing the solution.
Could you please provide me the cost analysis of Mivan Shuttering on any Live project with details.
Please mail me on my mail id.
Because I am going to start Mivan shuttering in one my mass housing project.
Regards
Imran Khan
imran.khan@rtechgroup.co.in
Regards,
Vamshi
vamshidhar994@gmail.com
Cosmos is one of the best leading Testing equipment manufacturers Manufacturers in Pune,Testing equipment suppliersin pune, Testing equipment in pune, Testing equipment.
Testing equipment manufacturers in pune
Testing equipment suppliers in pune
Testing equipment
Testing equipment in pune
Testing equipment in india
coach outlet
louboutin
kd 11 shoes
nike air max 97
retro jordans
yeezy boost 350 v2
fila
curry 6 shoes
curry 5
I really like all of your writing. I hope you don't get bored to always share your experiences with me. Don't forget to visit my website below:
https://www.merpatiku.my.id
https://www.petsofusa.com
https://www.healthzia.net
https://www.celanapria.my.id
House Renovations in Wimbledon
Accounting services in barking
Loft Conversions Southend on Sea
Best loft conversions Southend
tax return service in barking
clear tarpaulin
heavy duty tarpaulin