1. Aluminium Formwork System Step -1 :- Detail Drawing of Mock up Shuttering . Make Sure the building architectural & structural details shall be freezed before manufacturing / fabrication of Aluminum Shuttering. It could be cumbersome while executing the works if there is any revision in drawing Step 2:- Lets start executing the formwork. Fixing of Vertical wall reinforcement shall be done. Step 3:- Concrete Starters shall be done. Step -4 :- Fixing of Wall Panels as per above shown shuttering layout. Any electrical wall conduiting can be done prior to fixing of Aluminum Shuttering. Step -5 :- Fixing of Slab Panels after erection of vertical wall panels Step 6:- Concrete can be done after slab shuttering & conduiting is done. Step 7:- Vertical walls can be removed (Deshuttering) after 24 hours of slab casting. 2. Features of Alumi...