Skip to main content

High Rise Building Demolition - Bottom Up Method



Kajima Corporation Buildings – Demolition Methodology 
“There are so many quiet revolutions going on in tall buildings. Top-down construction is one such revolution, and here is another—bottom-up demolition.”


Location
TokyoCompletion Date
Tower 1: 1968
Tower 2: 1972
Demolition Date
2008
Height
Tower 1: 76 m (249 ft)
Tower 2: 65m (213 ft)
Stories
Tower 1: 20
Tower 2: 17
Primary Use
Office

The demolition of older tall buildings is increasingly becoming an issue with the impact on the environment and re-use of materials. The new Kajima method offers a solution which addresses and improves upon typical demolition methods. This method will improve the sustainability of a building through its lifespan and final deconstruction. Aside from improving sustainability, this method also decreases the impact of demolition on its surroundings.




Figure 1. Demolition sequence: March 08
Figure 2. Demolition sequence: May 08
Figure 3. Demolition sequence: July 08

A high-rise construction boom in Japan during the 1960s and 1970s has resulted in a large amount of aging towers. Building owners have an interest in demolishing the old structures to replace them with more modern, safe, and work-friendly buildings, but there are several issues to address in this process. 

The Kajima “Cut and Take Down Method” was developed to satisfy both safety and environmental concerns. In April 2007, Kajima started to develop this new demolition method to demolish its aging office headquarters buildings, which were 76 meters tall and 65 meters tall.

Buildings are usually demolished by placing heavy equipment and workers on the top floor and then lowering the waste material down to ground level. The “Cut and Take Down Method” alternatively allows the workers to start at the base and work their way up. By starting at the bottom, gutting one floor, and then lowering the entire building on jacks one floor at a time, all work can be performed safely at ground level.

Figure 2: Demolition process underway
On the 85 by 60 meter site, the two towers were situated quite close to another office building and a residential building, emphasizing the need for a clean, quiet demolition process. To accomplish this, temporary columns are used around the structural column grid, the existing columns are replaced, and then hydraulic jacks are placed where the existing columns were and the building can be lowered to the next floor plate where the process is repeated. 

The hydraulic jacks each had a capacity of 1,200 tons, and supported the structure through each cycle of lowering. A cycle would lower the whole building by 675 mm, which meant that five cycles were required for each floor (total of 3.375 meters). The total time to demolish a whole floor was six days: 2.5 days for lowering and the remaining time to demolish the rest of the structure.



Figure 3. Demolition process step 1: Cut the column. Cut length of 70 centimeters for a column and take off


Figure 4. Demolition process step 2: Extend the jack stroke. Extend length of 70 centimeters for jack stroke


Figure 5. Demolition process step 3: Take down all jacks. After doing step 1 & 2 for all columns, all jacks were taken down


Figure 6. Demolition process step 4: Take out beams and floor slab of the floor above

A “core wall and load transferring frame” system are utilized to temporarily reinforce the structure to prevent any lateral movements due to wind or earthquake forces. The core wall was 400–900 mm thick reinforced concrete and was placed in the center of the floor plates up to the third level to take any lateral forces of the superstructure. To ensure the transfer of lateral loads, the load transferring frame was installed in steel and connected to the existing structure. It was then tied into the core wall with a track-like system, which would lock in place in the event of an earthquake.

The new method allows the dismantled building to keep the same level of seismic and wind resistance capability as its original design. It also reduces the amount of noise as compared with typical top-down approaches, because all the work is being completed at the ground level. Safety of workers is increased as well, due to the location of all the work being at ground level as opposed to the building top.

Figure 7. Removing columns after cutting
In considering the reduction of site waste being sent to landfills, this new method allows for a more efficient system of recycling and reusing. The orderliness of the process means that the materials from each floor may be sorted effectively so the maximum amount of material is sent to its rightful place instead of batches of material getting sent to the landfill without adequate sorting. The Kajima Towers were able to be sorted into 30 types of materials for recycling, as opposed to a typical 20 at other demolition sites. The recycling rate was over 90% for the interiors of the buildings, surpassing the average 55%. 

Although this method was developed for a building with steel frame structure up to 20 stories high, it can be applied to larger-scale buildings as well. Furthermore, this process is especially useful in densely built areas where typical demolition may impact neighboring buildings. The demolition of the two Kajima Towers was completed in nine months for the 20- and 17-story buildings. Though the costs of this method may be 5–10% higher than traditional methods, the total time of demolition can be decreased by 15%, increasing the turnover rate of the site.

Figure 9. Core wall demolition


Comments

Anonymous said…
True, High rise building demolition time most important to be carefully use bottom up method. In bottom power is generated by a motor that runs on energy created when disassembled building components are lowered by crane through a hole punched in every floor. The electricity produced is stored in a battery.


Modular Buildings
UK Tarps said…
Thanks for sharing this post with us,
Extra Heavy Weight Tarpaulin

Popular posts from this blog

Construction Sequence of MEP works in Buildings

Typical Construction Sequence for Mechanical / Electrical / Plumbing Works in High Rise Building Grouping of MEP Fixes like PVC Electrical conduits in Slabs : 1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab) 2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ducting ii) Pressure tests and insulations iii) Installation of FCUs, water heaters (Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix) 3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc. (Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the ceiling tiles - too much coordination is required at

Mivan Shuttering Details

Details of Aluminum Formwork (Mivan / MFE) The most effective means available for the construction of high, medium and low rise mass housing R/C structures. It is a precision-engineered formwork fabricated in Aluminium. Monolithic pouring. Walls, columns, slabs & beam are poured together. Speed - Induces a disciplined & systemized approach to construction, which creates a daily work cycle, the essence of the productivity. The productivity generates a overall work cycle, that can achieve 4/5 day per floor outputs or other cycle times to suit your project requirements. It is flexible in design and can form any architectural or structural configuration, such as stairs, bay windows, curved features, etc. Quality - When struck the aluminium formwork reveals a good quality fair face onto which a 4–5mm skim coat can be applied for a perfect finish eliminating need of plaster. Provides an Integrated Scaffolding reducing the cost of your scaffoldi

List of Top 200 Construction Companies in the world

The world's 200 largest construction companies Position Company Country 2007 Posit ion Change 1 Vinci France 1 - 2 Bouygues' Construction Divisions France 2 - 3 ACS Spain 5 2 4 Bechtel US 3 -1 5 China Rail way Group China 6 1 6 China Rail way Construction Corporation China 23 17 7 Hochtief Germany 4 -3 8 Ferrovial Spain 11 3 9 China Co mmunications Construction Group China 14 5 10 Skanska Sweden 9 -1 11 FCC Spain 25 14 12 China Stat e Construction & Engineering (CSCEC) China 13 1 13 Eiffage France 21 8 14 Kajima Co rporation Japan 8 -6 15 Fluor US 17 2 16 Strabag S E Austria 22 6 17 Taisei Cor poration Japan 10 -7 18