Construction Sequence of MEP works in Buildings


Typical Construction Sequence for Mechanical / Electrical / Plumbing Works in High Rise Building


Grouping of MEP Fixes like PVC Electrical conduits in Slabs :

1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab)

2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling
i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ducting
ii) Pressure tests and insulations
iii) Installation of FCUs, water heaters
(Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix)

3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People
i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc.
(Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the ceiling tiles - too much coordination is required at this stage)

MEP 2nd Fix: Other Areas
Installation of all equipments like AHUs(Floor mounted), all pumps, heat exchangers(if any), bus bars, generators, water tanks etc.,

4. MEP Final Fix
Installation of Air terminals, sprinkler heads, wiring accessories, low current devices, CCTV, Public Address System (PAS), Isolators, fire fighting equipments(Hydrants), Sanitaryware, DBs, SMDBs & Dressing, SMA TVs, Structured Cabling, All Switch Points

External and other MEP works
i) Connections to Main lines of Govt. Authority, water supply, drainage, ETISALAT
ii) LV Room installations (MDBs, SMDBs, DBs)
iii) Installation of external piping, Manhole construction
iv) Installation of lightning protection, Backup System, Intercom System etc.,

Comments

Anonymous said…
Ram,

Nice Works. it is really useful
Unknown said…
Very Nice Blog Information!!

Thanks for sharing a very helpful information. Please keep up sharing...

Ceiling Tile
Anonymous said…
Scheduling is one of the most important things in construction!

You can check out The very best scheduling practices in Construction on our blog!
Unknown said…
Could anyone please explain sequence of work with flow chart diagram
Thanks for sharing this post with us, Please visit sivantafoundations Group to find out the residential properties in Chennai. sivantafoundations Group is Award Winning Real Estate company in Chennai. Construction companies in Chennai | Flats near Anna Nagar | Apartment In Madhavaram | Builders In Chennai
Whitearch said…
I agree with a lot of the points you made in this article. If you are looking for the mep contractors in uae, then visit Whitearch-me.com. I appreciate the work you have put into this and hope you continue writing on this subject.
gokul said…
Thank you for your feedback! I'm glad to hear that the post was useful to you. You can find a comprehensive guide to the MEP works sequence in Chennai on our website, which is a beneficial resource for Epc Companies In Chennai seeking a detailed understanding of the topic. We strive to provide insightful and informative content to our readers, and we appreciate your support.
ravi said…
"Insightful guide by Industrial Builders In Chennai. This blog elaborates the construction sequence of MEP works, offering valuable insights into efficient project management. A must-read for construction enthusiasts."
Arthy Rahul said…
Thank you for sharing this blog, Keep posting a lot, When it comes to superior steel building construction in Chennai, "Peb Contractors In Chennai" stand out as the premier choice. Renowned for their expertise, these contractors specialize in delivering top-notch pre-engineered steel buildings. Combining advanced technology with skilled craftsmanship, "PEB Contractors in Chennai" ensure sturdy structures that excel in durability and design. For unparalleled steel building solutions in Chennai, rely on the proven excellence of "PEB Contractors in Chennai".
UK Tarps said…
I have read your blog today. Even after so many years, it is still such useful content and very helpful to me.
Tarpaulin
This blog provides a clear and organized overview of the typical construction sequence for mechanical, electrical, and plumbing (MEP) Consultants in Dubai work in high-rise buildings. It highlights the step-by-step process, emphasizing the importance of coordination and timing between different teams involved in the construction. This structured approach ensures efficiency and quality in MEP installations for such complex projects.
We are now remodeling our Victorian-style house in London, Ontario, and our contractor is doing an amazing job paying attention to every little detail.
Home renovations in London, ON
anandhi said…
This comment has been removed by the author.
Anonymous said…
Looking for top-notch driveway repair? Look no further than Masonary Paving & Sealcoating! Our expert team specializes in restoring driveways to their former glory, ensuring durability and aesthetic appeal. Trust us to revitalize your driveway and leave it looking brand new. Contact us today for a consultation!
PGP-Links said…
Thanks for sharing this post with us, Check out the top demolition services in the UAE
Demolition Services in UAE
mahanhomes said…
Thank you very much for sharing the valuable blog with us. Keep sharing helpful information.

construction company in Ontario
PGP-Links said…
Looking for demolition services in UAE
or need help with offshore and onshore services in the UAE
? Visit my site for expert advice and tailored solutions. Check it out today!

Popular posts from this blog

Mivan Shuttering Details

Details of Aluminum Formwork (Mivan / MFE) The most effective means available for the construction of high, medium and low rise mass housing R/C structures. It is a precision-engineered formwork fabricated in Aluminium. Monolithic pouring. Walls, columns, slabs & beam are poured together. Speed - Induces a disciplined & systemized approach to construction, which creates a daily work cycle, the essence of the productivity. The productivity generates a overall work cycle, that can achieve 4/5 day per floor outputs or other cycle times to suit your project requirements. It is flexible in design and can form any architectural or structural configuration, such as stairs, bay windows, curved features, etc. Quality - When struck the aluminium formwork reveals a good quality fair face onto which a 4–5mm skim coat can be applied for a perfect finish eliminating need of plaster. Provides an Integrated Scaffolding reducing the cost of your scaffoldi

List of Top 200 Construction Companies in the world

The world's 200 largest construction companies Position Company Country 2007 Posit ion Change 1 Vinci France 1 - 2 Bouygues' Construction Divisions France 2 - 3 ACS Spain 5 2 4 Bechtel US 3 -1 5 China Rail way Group China 6 1 6 China Rail way Construction Corporation China 23 17 7 Hochtief Germany 4 -3 8 Ferrovial Spain 11 3 9 China Co mmunications Construction Group China 14 5 10 Skanska Sweden 9 -1 11 FCC Spain 25 14 12 China Stat e Construction & Engineering (CSCEC) China 13 1 13 Eiffage France 21 8 14 Kajima Co rporation Japan 8 -6 15 Fluor US 17 2 16 Strabag S E Austria 22 6 17 Taisei Cor poration Japan 10 -7 18