Skip to main content

Top Ten Construction Failures



Top Ten Construction Failures

10.) Tower of Pisa
No list of construction failures would be complete without this iconic engineering mishap. A mere three meter foundation and weak subsoil contributed to a nearly 5.5 degree lean until preservation crews were called in to help lessen the instability. The tower’s top is still more than 3.9 meters off center.
Tower of Pisa.jpg
9.) Tacoma Narrows Bridge
Opened in1940, the bridge was the third longest suspension bridge in the world before it collapsed in dramatic fashion just four months later. Sustained 40 mph winds caused a phenomenon known as aeroelastic flutter, resonating violently with the structure until the roadway broke apart and fell hundreds of feet into the gorge below.
TacomaNarrowsBridgeCollapse.jpg
8.) Hubble
One of the crowning achievements of the space age, the Hubble Space Telescope launched with a defective mirror that severely inhibited the quality of the incredibly expensive instrument’s imaging capabilities. Several servicing missions had to be flown to correct the issue, and Hubble ended up costing U.S. taxpayers nearly $6 billion – up from an original $400 million.
Hubble.jpeg
7.) Lotus Riverside Complex
In 2009, a recently completed residential building collapsed nearly intact in Shanghai, killing one construction worker. A lengthy probe pointed to excavated earth being dumped nearby, which caused a river bank to collapse and saturate the surrounding soil, causing the instability. The eleven remaining structures in the project were immediately investigated.
Lotus Riverside Complex.jpg
6.) New York City Crane Collapse
A 2008 crane collapse in a downtown NYC neighborhood resulted in the deaths of six construction workers and another female bystander. Investigators determined that instead of the recommended eight safety straps, negligent crews had installed only four, worn straps, leading to the deadly failure.
NYC Crane.jpg
5.) Hyatt Regency Walkway
During a tea dance in July of 1981, dozens of people gathered on an aerial walkway of the less than year-old hotel, before a catastrophic structural failure sent hundreds hurtling down four floors onto crowds of hundreds below. More than 200 people were injured and 114 lost their lives.
Hyatt Regency walkway.jpg
4.) Chicago Crib
As crews were working on a water intake tunnel for Chicago in 1909, a fire broke out on a water crib in the middle of winter, killing 60 workers and badly burning dozens of others, with many drowning or succumbing to hypothermia as they tried to escape the flames.
Chicago Crib Fire.jpg
3.) Quebec City Bridge
The 1907 construction of the Quebec City Bridge across the St. Lawrence River ended tragically after officials ignored the fact that initial calculations for the bridge were off by more than 8 million pounds. 75 workers lost their lives when the structure finally failed and plunged into the river below.
Quebec City Bridge.jpg
2.) Willow Island Cooling Tower
A 430-foot power plant cooling tower, under construction in 1978, was severely behind schedule, resulting in a number of shortcuts and oversights that led to a collapse claiming 51 lives. Unset concrete and poorly constructed scaffolding were the main factors behind the structural failure.
WillowIslandCoolingTower.jpg
1.) Teton Dam
While many of these construction failures resulted in tragic loss of life, they have helped shape the safety procedures and guidelines that have saved countless lives over the years.
The Teton Dam, for example, was an earthen dam built by the federal government in southeastern Idaho which broke apart upon its first filling on June 5th, 1976. The rushing waters from the catastrophic failure killed 11 people and drowned more than 13,000 head of cattle, with damages estimated up to $2 billion.
Permeable soil and cracked foundations were blamed for the dam’s collapse, which allowed more than 2,000,000 cubic feet of water per second to careen into the Teton River canyon, emptying the reservoir within hours. The Dam’s failure prompted a round of more stringent regulations governing similar projects across the United States.
Teton Dam.jpg


Comments

Popular posts from this blog

Construction Sequence of MEP works in Buildings

Typical Construction Sequence for Mechanical / Electrical / Plumbing Works in High Rise Building Grouping of MEP Fixes like PVC Electrical conduits in Slabs : 1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab) 2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ducting ii) Pressure tests and insulations iii) Installation of FCUs, water heaters (Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix) 3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc. (Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the ceiling tiles - too much coordination is required at

Mivan Shuttering Details

Details of Aluminum Formwork (Mivan / MFE) The most effective means available for the construction of high, medium and low rise mass housing R/C structures. It is a precision-engineered formwork fabricated in Aluminium. Monolithic pouring. Walls, columns, slabs & beam are poured together. Speed - Induces a disciplined & systemized approach to construction, which creates a daily work cycle, the essence of the productivity. The productivity generates a overall work cycle, that can achieve 4/5 day per floor outputs or other cycle times to suit your project requirements. It is flexible in design and can form any architectural or structural configuration, such as stairs, bay windows, curved features, etc. Quality - When struck the aluminium formwork reveals a good quality fair face onto which a 4–5mm skim coat can be applied for a perfect finish eliminating need of plaster. Provides an Integrated Scaffolding reducing the cost of your scaffoldi

List of Top 200 Construction Companies in the world

The world's 200 largest construction companies Position Company Country 2007 Posit ion Change 1 Vinci France 1 - 2 Bouygues' Construction Divisions France 2 - 3 ACS Spain 5 2 4 Bechtel US 3 -1 5 China Rail way Group China 6 1 6 China Rail way Construction Corporation China 23 17 7 Hochtief Germany 4 -3 8 Ferrovial Spain 11 3 9 China Co mmunications Construction Group China 14 5 10 Skanska Sweden 9 -1 11 FCC Spain 25 14 12 China Stat e Construction & Engineering (CSCEC) China 13 1 13 Eiffage France 21 8 14 Kajima Co rporation Japan 8 -6 15 Fluor US 17 2 16 Strabag S E Austria 22 6 17 Taisei Cor poration Japan 10 -7 18