MS PROJECT FOR CONSTRUCTION SCHEDULERS
Table of Contents
List of Tables ................iii
List of Figures ................iv
Abstract ................v
1. Introduction ................1
2. MS Project Differences ................2
3. Tracking a schedule with MS Project ................4
3.1. Schedule Set-up ................5
3.2. Setting a Baseline ................8
3.3. Updating the schedule ................10
3.3.1. Updating Tasks ................10
3.3.2. Observing the Status Date ................15
3.3.2.1. Reschedule Uncompleted Work to Start After ................16
3.3.2.2. Status Date Calculation Options ................17
3.4. Comparing Schedules ................22
3.4.1. Identifying Variances ................22
3.4.2. Identifying Revisions ................23
4 Conclusion ................23
Bibliography ................25
Table 1, MSP Calculation Rules ................11
List of Figures
Figure 1 Remaining Duration in the Past ................3
Figure 2 MSP observes Data Date using constraints ................4
Figure 3 Recommended Status Date Selection Setting ................5
Figure 4 Schedule Options Tab ................6
Figure 5 Calculation Options Tab ................7
Figure 6 Set Baseline Screen ................9
Figure 7 Sample 10-Day Activity ................11
Figure 8 Result of Entering % Complete ................11
Figure 9 Result of Adjusting Remaining Duration ................12
Figure 10 Update Tasks Form ................12
Figure 11 Task Information Form ................13
Figure 12 Task Details Form ................13
Figure 13 Tracking Table ................14
Figure 14 Update Progress Screen ................15
Figure 15 Update Date Screen ................16
Figure 16 Status Date Screen ................17
Figure 17 Sample Schedule with Future Actual Dates ................17
Figure 18 Status Date Options ................17
Figure 19 Task with incomplete Work in the Past ................19
Figure 20 CPM Option to Move Incomplete Work Out of the Past ....19
Figure 21 Result of Moving Incomplete Work Out of the Past ...........19
Figure 22 Additional CPM Option for Incomplete Work ................19
Figure 23 Result of Moving Complete Work to the Status Date .........19
Figure 24 Sample Schedule with Complete Work in the Future .........20
Figure 25 Future Options ................20
Figure 26 Result of moving end of complete work back to status date 20
Figure 27 Sample Out of Sequence Progress ................21
Figure 28 Retained Logic ................21
Figure 29 Effects of Zero Remaining Duration ................21
Figure 30 Gantt Chart Wizard ................22
Abstract
Despite some detractor’s opinions, Microsoft Project (MSP) CPM scheduling software is here to
stay as many contracts are now mandating its use. Most people using MSP on construction
projects find that MSP is fine for planning the work but very difficult to use when maintaining the
status and forecasting accurate project completion. MSP is also difficult to use when performing
delay analyses. The good news is that you can ‘make’ MSP properly reflect the consequences of an
update displaying proper Retained Logic. This paper will explain how to best use MSP in place of P6 or other more status-oriented scheduling software.
1. Introduction
Over the last two decades Primavera products became the predominant scheduling software of the
construction industry worldwide. Sadly, nothing lasts forever and many contracts have recently
started to specify MS Project (hereinafter referred to as, “MSP”) as the required scheduling
software.[1]
MSP has its advantages; it costs less than many of its competitors and it is ‘user-friendly’. It is easy
to start scheduling activities immediately. MSP easily produces decent default graphics and
reports. Another reason for MSP’s popularity is that a majority of US Federal Government PCs
come equipped with MSP. It is difficult to justify requesting the authority to purchase another
scheduling software when you already have one installed on your computer ‘for free’.
Most construction contracts for construction projects require periodic schedule updates. A
schedule update is an assessment of the project status and prediction of how and when the project
will be completed. Proper updating of the work schedule is an integral part of project management
and a critical communication tool between the parties. The schedule update should reflect the
current plan to reach project completion and an accurate record of the past performance. The
major steps in updating a schedule involve:
1. Setting a baseline
2. Updating the schedule
3. Comparing schedule updates
These steps are common to every software package and considered a regular course of business for
construction schedulers. MSP has many unique features specifically designed to make using the
software simple. However when it comes to updating a schedule using MSP, construction
schedulers often find MSP extremely confusing. This is mainly due to the MSP’s ‘ease of use
features’ getting in the way of reflecting the consequences of the current status. It gets even more
complicated if you ever have to do a forensic delay analysis on a MSP schedule. Cheer up, as all is
not lost. A clear understanding of how MSP calculates a schedule will make it possible to properly
use MS Project in place of a Primavera product, if needed.
This paper documents the complete process of tracking a schedule in MSP as well as the details of
how to ‘make’ MSP properly handle a typical status update involving out-of-sequence status.
2. MS Project Differences
There are a few operational differences between MSP and the Primavera products. Because MSP is
a Microsoft product, all work is performed in computer memory and you only save any changes
made if you tell the program to perform this operation. With products such as P6, all changes are
registered as soon as you press the Enter key. Because of the computer memory-centric scheme,
even in a multi-tasking environment of MSP Server, only one person can view the schedule at a
time.
MSP calls float values with the term, “Slack” and lists 0 as the value of slack for completed
activities. Finally, MSP only allows for one relationship between any two activities. This prevents
using the Start-to-Start and Finish-to-Finish relationship pairs found in P6 schedules.
MSP has unique concepts like Deadlines, and Recurring Tasks. In some cases, familiar scheduling
terms work different in MSP. For example “Multiple Critical Paths” in MSP means basically make
open ends critical. In some areas MSP lacks CPM functionality; for example the designation of a
longest path does not exist in MSP. For detailed explanation of MSP features and functionality, a
book such as Planning and Scheduling Using Microsoft Office Project 2007 [3] by Paul E. Harris can be consulted.
The differences in the internal computational factors are even more significant. It is crucial to
understand how MSP calculates the schedule before delving into the mechanics of statusing a
schedule. Since most construction schedulers are familiar with Primavera, it is easier to compare
MSP to Primavera to point out the major differences.
Primavera considers every activity in the schedule when computing a CPM, even those that are
statused as complete [2]. Unless overridden by a constraint, all activities without a predecessor are
scheduled (with consideration to their calendars) to begin on the current data date (early start) and
their remaining durations/relationships are used to compute their early finish. This rule even applies to completed activities with a remaining duration of zero. After all CPM calculations are complete, Primavera then goes back to the completed and in-progress activities and overrides the calculated dates with the actual dates. This process allows Primavera to consider the delaying effects of uncompleted work due to out-ofsequence progress under the Retained Logic calculation rule. Consequently, the Primavera Data
Date is the starting point and a fundamental piece of information for CPM calculation.
In contrast to P6, the default method of calculation for MSP does not require the scheduler to set a
Status Date (Primavera names it Data Date). This is simply, because MSP does not use the Status
Date to calculate the dates in the schedule. Instead MSP starts with the Project Start Date and
calculates the schedule using CPM rules even for the activities with actual dates. If an activity has
actual dates, the calculated CPM dates are ignored and the actual dates are used for calculating the
next activities’ start or finish dates. This is similar (but still different) to the P6 CPM calculation
mode, “Actual Dates.”
As shown in Figure 1 below, this process creates a potential for inherently flawed schedules with
remaining durations in the past or actual dates in the future. Both P6 and MSP suffer from allowing
actual dates in the future. P6 and MSP differ from how they handle incomplete work in the past.
Common sense and CPM rules require that activities with remaining duration scheduled in the past
must be ‘moved’ into the future. It defies logic to say “We will complete this work last month”.
Even though MSP is not designed to calculate the schedule from the Status Date, there are option
settings available in MSP to simulate CPM calculations based upon a Data Date. This somewhat
complicated process involves the use of built-in routines that add activity constraints and adjusts
some internal dates.
For MSP to simulate the effects of a Data Date, all unstarted tasks are given a Start-no-earlier-than
constraint date equal to the status date and all started but incomplete tasks have their Resume
Date set to the Status Date. This method delays the incomplete and unstarted tasks to the Status
Date. During this process, tasks with constraints lose their previously set constraints and tasks that
never had a constraint before now get a constraint. This is not desirable, but unfortunately it is the
only way that MSP observes the Data Date. Figure 2 below displays, the constraints assigned by
MSP to observe the Data Date.
3. Tracking a schedule with MS Project
The complete process of tracking a schedule involves setting a baseline, updating schedule status
and comparing the updates to the baseline or previous updates. For brevity, this paper assumes
that the reader is familiar with MSP user interface as well as its basic functionality and deals mainly
with general steps that an experienced construction scheduler would understand or expect.
Therefore starting with the schedule set up, we will cover setting a baseline, updating the schedule
and comparing the update to the baseline without detailed step by step instructions.
3.1. Schedule Set-up
Before explaining the details of schedule update process, it is crucial that the correct options are
selected and relevant points in time are displayed. MSP was designed to not rely on the Data Date.
There is Status Date which deceptively sounds like the Data Date in Primavera, but it is not the
same. Instead MSP relies on the Project Start date for calculation.
There is also a MSP Current Date which is the date of the computer when the file is open. If there
is no Status Date set then the Current Date is used for calculating earned value. Neither Current
Date nor the Status Date is used for calculating schedule dates and neither has any scheduling
significance. Neither of these dates is shown on the Gantt chart by default unless the user adds
them to the view. To reduce confusion, it is recommended that the Status Date line be displayed in
the Gantt views and Current date should not be displayed.
Figure 3 shows the recommended selection setting.
It is difficult and confusing to implement changes to the CPM calculation modes after an activity is
added. To prevent errors and confusion, we strongly recommend that you configure your MSP
schedule before adding the first activity. The recommended set-up steps are as follows,
- Under the Tools / Options / Schedule Tab. Figure 4 shows this tab.
Figure 4 – Schedule Options Tab
Split in-progress tasks: [Checked] This option allows rescheduling of remaining duration and work
when an in-progress task is running longer than originally planned.
Tasks will always honor their constraint dates: [Unchecked] This option tells MSP to schedule tasks
according to their constraint dates, regardless of logic. Clear the check box to specify that task
constraint dates with negative slack (float) move according to their relationships with other tasks
rather than be solely scheduled according to their constraint dates.
- Under the Tools / Options / Calculation Tab. Figure 5 shows this tab.
Figure 5 – Calculation Options Tab
Updating task status updates resource status: [Checked] This option insures that task resource
status does not override update status.
Move the end of completed parts back to status date: [Unchecked] This option prevents actual
dates later than the Status Date (in the future.) It also changes Actual Dates without user input.
This is dangerous to do. ‘Bad’ Actual dates should be flagged, but not automatically changed. P6
allows actual dates in the future but does note these as warnings in the Schedule Log produced.
and move start of remaining parts before the status date forward to status date: [Unchecked]
This option ‘recovers’ dangling work left over after moving completed parts back to the status date.
This step is unnecessary, as the remaining work will be scheduled after the Status Date.
Move the start of remaining parts before the status date forward to the status date: [Checked]
This option prevents uncompleted work from being scheduled before the Status Date (in the past.)
and move end of completed parts forward to status date: [Unchecked] This option will move
complete parts of split tasks to the status date and will assign new actual dates.
3. Because we are going to be splitting tasks, any tasks created must not be assigned Task Duration
Type of, “Fixed Duration.”
These options may NOT be turned on and off to recalculate all tasks. The options only work on new
tasks when they are added to a schedule or when a task is updated by changing the % Complete.
This is why we address these settings before you begin adding activities to your MSP schedule.
3.2. Setting a Baseline
Establishing a baseline is the first step in monitoring your schedule. The term, “Baseline” can be
confusing here as MSP (and P6) uses this word to mean something slightly different than from its
universal use in the construction industry.
The construction industry labels a schedule as a Baseline Schedule if it is the first approved,
complete schedule on the project. This type of Baseline typically does not have any status
recorded against it. MSP and P6 calls a baseline schedule any copy of the schedule that is stored
‘internally’ in another schedule. This type of baseline is used for comparison purposes. In this
paper, we will call the initial construction schedule a Baseline Schedule (using capitol letters) and
the MSP schedule copy, a baseline schedule (with lower case letters.)
When a baseline schedule is made, MSP copies Early Start and Early Finish dates to the baseline
Start and Finish Date fields. Original Duration gets copied to baseline Duration. Each Task’s Costs
and Work is copied to baseline Costs and Work fields. Nothing else is saved in a baseline schedule.
See Figure 6, Set Baseline Screen.
MSP treats the baseline as a snapshot of your schedule at the time that you created the baseline.
MSP does not store logic, float or constraints for the baseline and as a result, can not recalculate
any of the stored information. P6 users familiar with baselines will assume that they can convert
(or ‘unattach’) a baseline schedule back into a fully functional schedule. This is not the case with
MSP. Due to the fact that MSP baseline schedules do not store complete activity and logic
information, creating a MSP baseline is a ‘one-way’ process.
Baseline information can also be edited manually. Since baseline fields are editable by Users and
will not be recalculated by MSP, users should be cautious if they decide to change any of the
baseline information manually. The fact that it is all together too easy to accidently change this
information makes relying on the variance information more risky than with the typical
Target/Update procedure used with P3.
MSP allows for a maximum of 11 baselines. This is barely enough baseline storage for a 12-month
project without any Change Orders or Time Impact Analyses baselines. Users are strongly
encouraged to keep separate monthly backups in order to maintain and be able to prove past
status integrity.
There is also another MSP feature called, “Interim Plan” which has similar functionality as the
creation of baselines. This feature stores less information than a baseline. The Interim Plan
function only stores the Early Start and Early Finish dates of tasks and not durations, costs, or work.
An interim plan can be compared against a baseline plan or current plan to monitor project
progress or slippage. MSP allows up to 10 Interim Plans.
MSP allows Summary Tasks to be added, deleted, and moved around. If a task is added, deleted, or
moved after the baseline is set, the baseline dates for Summary Tasks become invalid. MSP has a
feature called Roll Up baselines that would reset the baseline dates for Summary Tasks.
Another important issue with the baseline is that the Late Start and Late Finish dates are not
stored. All variance measurements are assessed from the early dates. Available float
considerations are not taken into account and are not part of the baseline history.
3.3. Updating the schedule
3.3.1. Updating Tasks
The first step in updating the MSP schedule is to understand how durations are calculated. Task
durations are comprised of four important pieces of information:
1. Duration (which is equal to Actual + Remaining Duration)
2. Actual Duration
3. Remaining Duration
4. % Complete (which is equal to Actual Duration / Duration)
The calculation of MSP Actual and Remaining durations is confusing to many schedulers, especially for those who are used to Primavera products. First in Primavera, actual duration is calculated based the activity’s actual date and the Data Date (or Actual Finish date if it exists) whereas in MSP, the Status Date is not used in calculating actual durations.
Another reason for confusion is because MSP automatically links Duration, Actual Duration,
Remaining Duration and % Complete without an option to remove the link. Only any two of these
are independent, and the rest are calculated using the formulas listed above.
The scheduler needs to understand how these four pieces of information are calculated in MSP.
Table 1 below summarizes the interaction between these 4 duration-related task properties.
Table 1 – MSP Calculation Rules
To illustrate how each of these fields is calculated, let’s review a simple activity with 10-day
duration as shown in Figure 7.
Figure 7 – Sample 10-Day Activity
Entering 20% complete will automatically assign an Actual Start date and calculate the Actual
Entering 20% complete will automatically assign an Actual Start date and calculate the Actual
Duration and Remaining Duration. Actual Start will be set equal to the Start date (for unstarted
tasks, MSP Start date field equals to early start date) of the Task as shown in Figure 8.
Actual duration will be 2 days, which is 20% of the Duration. Remaining Duration will be 8 days which is Duration minus Actual Duration. If we further adjust remaining duration to 10 days, the Duration will become 12 days as shown in Figure 9. This is 10 days remaining plus 2 Days actual. % Complete will be 17%, which is Actual Duration divided by Duration.
Actual duration will be 2 days, which is 20% of the Duration. Remaining Duration will be 8 days which is Duration minus Actual Duration. If we further adjust remaining duration to 10 days, the Duration will become 12 days as shown in Figure 9. This is 10 days remaining plus 2 Days actual. % Complete will be 17%, which is Actual Duration divided by Duration.
Figure 9
MSP provides 4 different ways to enter actual data for each Task.
1) Using the Update Tasks Form as shown in Figure 10 is one way of entering actual data for each
task. This method is the least preferred method because the form has to be closed after updating
each task and opened again after selecting the next Task. This makes it very cumbersome to
MSP allows you to use this function to update multiple tasks at once but the limitation is that MSP
assigns the same value to all. Therefore unless all Tasks have the same update information, this
function is not useful.
2) Another available update method is using the Task Information form as shown in Figure 11. This
is also a cumbersome way of updating because the form has to be closed after each update and
Figure 11 – Task Information Form
3) Using the Task Details Form to update the schedule is a less cumbersome method compared the
previous 2 methods listed above. Task Details (as shown in Figure 12) can be opened by dragging
the divider line and selecting Task Details Form from View, More Views. If a Finish date is entered
without task being 100% complete, MSP will automatically add a Finish Constraint to the Task. For
this reason, this third option is also not recommended.
Figure 12 – Task Details Form
4) The easiest and most efficient method to enter activity actual date status is by using the Tracking
Table in the Gantt Chart or creating your own table as shown in Figure 13. It is recommended that
the following fields are shown on this custom table.
Once the detail tasks are updated, the summary tasks inherit status data from their detail tasks.
Actual start is assigned to the Summary task when a detail task has been given an actual start and
similarly Actual Finish is assigned when all detail tasks have been assigned actual dates. A
Summary Task’s % Complete is calculated by dividing the sum of all Detail Tasks Actual Durations by the sum of all Detail tasks Durations.
MSP has a somewhat unusual feature that allows the scheduler to manually update Summary
Tasks. It is unlikely that this feature will be used by construction schedulers. The reason that we
say this is that a manual update of a Summary Task affects all the detail tasks below it. If a %
Complete is entered at the Summary level, MSP assigns values for Actual Duration, % Complete,
Actual Start and Actual Finish all the children tasks (Summary or Detail). Calculation of these
values differs based on the “Updating Task Status Updates Resource Status” setting. If “Updating
Task Status Updates Resource Status” is checked, the tasks are statused as if they were completed
per plan. If not checked, then all of the children tasks get the same % Complete value of the
Summary task. This is obviously a dangerous procedure to employ if the accuracy of individual
activity status is desired.
MSP has a feature called Update Progress which will automatically update the activity as if it
progressed as planned. This feature automatically sets the Actual Start, Actual Finish, % Complete
and Remaining Durations. There are 2 options available under this feature as shown in Figure 14.
Set 0% -100% Complete - Selecting this option will set Actual date to Early Start. Actual Duration
and % Complete will calculated based on the date entered in “Update Work As Complete Through”.
date is later than Finish date of the Task. Selecting this option will not reset the Status Date.
Either of these options can be applied to the selected Tasks or for all Tasks in the schedule.
Scheduler must be careful using this feature for various reasons. First, if Set 0% or 100% Complete
option is selected, the “Update Work As Complete Through” date and the Status Date might not
match. To make things worse, remaining durations will not move to any of these two dates,
resulting in remaining durations scheduled to be complete in the past. Similarly, if this feature is
applied only to ‘Selected Tasks’ then there is a possibility that there will be unstarted activities in
the past. Set 0% -100% Complete would produce reliable results only if everything is going per
plan. Therefore this feature is very limited in its use and not recommended.
3.3.2. Observing the Status Date
As explained above, MSP was not designed to calculate estimated schedule dates using the Status
Date. Forcing MSP to observe the Status Date is very complicated process that requires
understanding the calculation options in conjunction with using the “Reschedule Uncompleted
Work” on the Update Project form.
3.3.2.1. Reschedule Uncompleted Work to Start After
To properly update a schedule first we need to understand “Reschedule Uncompleted Work to
Start After” feature available on the Project Update form shown in Figure 15.
Figure 15 – Update Date Screeen
Figure 15 – Update Date Screeen
For this feature to work properly, ‘Split in Progress Tasks’ must be selected under the Tools,
Options Schedule tab.
When this feature is used, MSP will go through each unstarted task and will assign a Start-No-
Earlier-than-Constraint equal to the Update Project Status date. Understand that MSP only allows
one early constraint per task. Because of this, if any of those unstarted tasks had a different
constraint, the existing constraint will be deleted in favor of adding the new CPM constraint. Tasks
that are in progress will have their Resume Date set to the Update Project date.
Another disadvantage to this process surfaces if one is required to destatus the project. To do so,
the scheduler has to review each activity and remove the constraints and adjust the task splits
manually. This makes it very difficult and time-consuming for analysts to perform schedule what-if
analyses.
In addition, MSP does not change the Status Date to the date specified in the Update Project
feature (Figure 15.) This often results in confusion as the date specified in Update Project screen
(Figure 16) is not displayed on the Gantt chart and might end up being a different date than the
one that is displayed. To avoid confusion and to display a correct Status Date on Gantt view, the
Figure 16
Scheduler should set the Status Date same as the date specified during Project Update function as
Scheduler should set the Status Date same as the date specified during Project Update function as
shown in Figure 15.
Coordinating the date between the two screens only solves half of the problem because it moves
in-progress activities after the Status Date. As shown below in Figure 17,
there still can be tasks in the future with actual dates. Unlike with P6, there is no automatic notice in the CPM computations report.
3.3.2.2. Status Date Calculation Options
MSP 2002 [4] and later versions have four CPM Options to force MSP to observe the Status Date. A combination of options under the Calculation tab is shown in Figure 18.
These options move tasks around the Status Date, change assign actual dates to automatically
prevent incomplete work in the past, and complete work in the future. These options based on
their titles seem self-explanatory but have unexpected consequences for the unwary scheduler.
First of all for these options to function properly one must ensure that:
• Split in Progress Tasks option must be selected,
• Desired options must be selected before tasks are added,
• Updating Task Status updates resource status option must be checked,
• Task Duration type must be something other than Fixed Duration.
These functions are limited because:
• The options only work on new tasks.
• The options only work if tasks are updated using % Complete. If the task has 0% progress,
these options will not apply therefore unstarted tasks in the past will remain in the past unless the
scheduler runs project update form “Reschedule Uncompleted Work to Start After” feature
• Changing the options will not recalculate the CPM to display the effects of that change.
• If a Status date is not defined, MSP will use the Current Date without warning the user.
Tasks only reflect the CPM options if the tasks are updated by using % Complete. Changes to task remaining duration will be reflected in the schedule, but not the effects of the changed option rules. Therefore if tasks are updated by using anything other than % Complete, these functions are not implemented, even if later set. This method of update is problematic as AACE Recommended Practice 53R-06 [5], recommends updating an activity’s status by indicating the new remaining duration estimate rather than indicating a new % Complete. Preventing Incomplete Work in the Past
Logic tells us that you should not display planned work prior to the Data Date. This inconsistency in
status ‘hides’ work that must still be completed, ignores required resources, and disrupts the
correct calculation of planned dates for future work.
To illustrate how these options work, let’s look at a simple schedule shown below in Figure 19
To prevent incomplete work in the past options shown in Figure 20 should be selected
With these options selected, entering a % Complete value would assign an Actual start and move
remaining part of the task after the Status Date as shown in Figure 21.
If the following option as shown in Figure 22 is checked
in addition to the one described above.
The task split will be removed, actual start date will be changed, and the complete portion of the
task will be moved to the Status Date as shown in Figure 23.
Figure 23
This option will override any previously assigned actual dates; therefore it is recommended that it
remains unchecked. Assigned actual dates should never be automatically deleted.
Preventing Complete Work in the Future
To illustrate how these options work, let’s look at a simple schedule shown below in Figure 24.
In this example start of Task 1 is constrained to start no earlier than 20SEP10.
To prevent complete work in the future options shown in Figure 25
should be selected.
If the task is updated by entering a % Complete, the actual duration portion of the task will be
moved to the Status Date and an actual date to match will automatically be assigned to the task.
Selecting “And move start of remaining parts back to Status Date” sounds like the “Progress
Override” option in Primavera products. This is not correct as this option will also override existing
constraints. If the task has a constraint, selecting this option will erase it and bring the remaining
part of the task back to the status date.
The Results of our Settings
Now that we have our activities observing the Data Date, we need to compare this to what is
presented in P6 software. For demonstration purposes, we will take the typical 4-activity schedule
with out-of-sequence progress like that as shown in Figure 27 below.
When the out-of-sequence activity (in this case, Activity 2) has some remaining duration, then the
CPM Calculation Options forces the schedule to resemble Retained Logic as seen in Figure 28
below,
When the same out-of-sequence activity has no remaining duration, then the CPM Calculation
Options forces the schedule to resemble Progress Override as seen in Figure 29 below.
This ‘hybrid’ behavior is similar to that displayed with the P6 Actual Dates CPM calculation option.
As seen with the examples above, using these options has serious implications of automatically
changing or assigning Actual Dates. Therefore the scheduler should clearly understand these
options before using them. If the scheduler is not comfortable with these options, the same results
can be achieved by using the “Reschedule Uncompleted Work to Start After” on the Update Project
form except for preventing Actual Dates in the future.
Activities with progress that are in the future can be identified by running a filter and then can be
manually corrected. This is no different than using Primavera products since none of the Primavera
products have a built-in feature to prevent assigning actual dates in the future.
3.4. Comparing Schedules
It is important to realize that there will be changes to the schedule logic as well as differences
between the planned progress and actual progress. Changes to the schedule logic and planned
durations are revisions to the schedule and they will be calculated to take place in future to the
right of the status date. Other variances due to the performance will be in the past to the left of
the data date. Variances in the performance should be handled separately from the logic revisions
and planned duration changes.
3.4.1. Identifying Variances
To identify variances in performance, Start Variance and Finish Variance columns can be used. In
addition, schedulers can create custom bar styles to display baseline and schedule update
information in the same view. MSP has a Gantt chart wizard (Figure 30) that allows users to create
these views easily and quickly however schedulers should be aware that using this wizard will
overwrite any existing custom formatting.
For a more detailed analysis, the actual dates and planned dates can easily be extracted from MSP
and moved to an Excel spreadsheet or to MS Access database to perform a Daily Delay Measure
analysis (MIP 3.2) [6] This can be further automated using Excel or Access formulas and macros.
Remember, that we can only note variances to the early dates and not the late dates. Variance
analysis cannot take activity float into consideration.
Figure 30 – Gantt Chart Wizard
3.4.2. Identifying Revisions
MSP 2007 has a Compare Project Versions utility to review differences between two similar MSP
schedules. The Compare Project Versions utility compares tasks and resources only and does not
compare resource assignments. This utility produces a comparison report which looks like a
project schedule. Although this report displays color coding and indicators that provide
information about tasks and resources, it is extremely hard to understand, especially for schedulers
who have been using Claim Digger or SureChange.
On the other hand, MSP has a powerful Visual Basic for Applications (VBA) programming language which allows a quick development for custom comparison software. MSP users can create their own comparison routines and easily create their own variance reports. Exporting schedules to MS Access and using it to compare the two similar schedules is another option open to the scheduler. A quick survey noted third-party software providers who specialize in MSP comparison tools to include the following,
• Acumen Fuse
• Project Analyzer
4 Conclusion
MSP is inexpensive, very user friendly (especially for beginners) and provides decent default
reports and graphs. A casual user of MS Office with no scheduling experience can pick MSP up and
quickly create schedules. However a seasoned scheduler working on a construction contract is
likely to struggle with updating and maintaining the schedule. Some of the “ease of use” features
function at the expense of the CPM theory, which become sources of confusion for a seasoned
scheduler. The main areas are:
1) MSP Baseline management is cumbersome and confusing for the average scheduler.
2) MSP updating method of using % Complete is not suitable for construction schedules.
3) MSP Data Date issues which in effect complicate the schedule update process are confusing for construction schedulers.
4) Due to the difficulty of using MSP to note uncompleted work before the Data Date, the difficulties in removing status for what-ifs, and the difficulty in identifying variances between a series of MSP schedules, it is hard to do most types of delay analysis (except perhaps RP 29R-03 [6] MIP 3.1 and 3.2)
5) Due to all of the built-in update help routines that automatically insert made-up actual dates and remaining durations, it is difficult to assume that most MSP schedules contain accurate enough status data that is necessary for a detailed analysis.
Of course this does not mean that MSP cannot be used for construction scheduling. MSP is here to stay as many contracts are now mandating its use. This only means that construction schedulers must be proficient in MSP in addition to the Primavera products.
Comments
MS Project Training
bestpmptraininginchennai