Skip to main content

Tower Crane - Design Details

Design Check for Crane Supporting Boom for the Crane


The Crane tower needs to be supported laterally at certain interval from the RCC Building.

The interval can be say 30m.



The manufacturer has given a lattice section to be used as a lateral supporting member.

Check the capacity of the member under compression:

A = 4 Nos X 7.44 Cm2   = 29.76 Sq.m
L = 11m
I = A.x2   = 4 ( 7.44 X (30/2 - 1.81)2 )
I = 5177 Cm4

Therefore,   r =   I/A =   5177/29.74 = 13.1 cm

Therefore l/r min  =
        
                = 950 Kg/cm2

Therefore, Capacity of the section under compressive load =  σa.A

= 950 Kg/cm2    X 29.76 cm2

Pc = say 28T

In the absence of any specific load data,

Assuming maximum force in the connecting member can be plus/minus 10T maximum, the member seems to be safe.


The actual length of the member can be checked as per the site condition and the length of the member can be extended up to 11m as required upto splice joint.







(II) End Anchorage at the building slabs:

Try 6 Nos of M16 bolts to resist the force of 10T.
Assuming permissible shearstress = 1000 Kg/Cm2
Shear Capacity of one M16 bolt
= σss x net area
= 1000X 0.75 X П / 4X (1.6) 2
= 1000X1.5
= 1500 Kg

Total Force resisted by 6 Bolts = 6 X 1.5T = 9T < 10 T


Try M20 Bolts,

Shear capacity = 1000 X 0.75 X П / 4X (2) 2
                                       = 2355 Kg

Therefore Total Force Resisted by 6 Bolts

= 6 X 2.3T = 13.8 T > 10 T

Therefore, Provide 6 Nos M25 Bolts to connect the member with the building.








As per calculations, Crane tie should be provided in 7TH Floor, 14TH Floor and 19TH Floor respectively.

Comments

Popular posts from this blog

Construction Sequence of MEP works in Buildings

Typical Construction Sequence for Mechanical / Electrical / Plumbing Works in High Rise Building Grouping of MEP Fixes like PVC Electrical conduits in Slabs : 1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab) 2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ducting ii) Pressure tests and insulations iii) Installation of FCUs, water heaters (Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix) 3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc. (Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the ceiling tiles - too much coordination is required at

List of Top 200 Construction Companies in the world

The world's 200 largest construction companies Position Company Country 2007 Posit ion Change 1 Vinci France 1 - 2 Bouygues' Construction Divisions France 2 - 3 ACS Spain 5 2 4 Bechtel US 3 -1 5 China Rail way Group China 6 1 6 China Rail way Construction Corporation China 23 17 7 Hochtief Germany 4 -3 8 Ferrovial Spain 11 3 9 China Co mmunications Construction Group China 14 5 10 Skanska Sweden 9 -1 11 FCC Spain 25 14 12 China Stat e Construction & Engineering (CSCEC) China 13 1 13 Eiffage France 21 8 14 Kajima Co rporation Japan 8 -6 15 Fluor US 17 2 16 Strabag S E Austria 22 6 17 Taisei Cor poration Japan 10 -7 18

Tallest Building under construction