Skip to main content

How does the height of building calculated?


This tall building height calculator is developed to assist in determining tall building heights when only the story count is known. The calculator is divided into three categories representing the three major functions represented in tall buildings;
             (i) Office
             (ii) Residential/Hotel
             (iii) Mixed-use or when the function unknown

The calculator will provide an approximate height for a single tall building, but as tall building characteristics vary significantly with location, structural material, form, profile, etc, in some instances estimates will vary considerably with actual building height. As such, the calculator is best utilized to determine heights in multiple building / statistical studies, where there are many unknown building heights. In these instances the greater number of buildings examined will reduce any overall variations.

The calculator does not include any factors for spires or any other major projections at the roof plane, due to the wide ranging nature of these.

The height calculator is never utilized by the CTBUH to determine any building heights as part of the CTBUH tall building database i.e. all published heights within the CTBUH database are accurate, confirmed heights according to published data.


Height Calculator Assumptions

OfficeResidential/hotelFunction Unkown or Mixed-Use1
floor-to-floor height (f)3.9m3.1m3.5m
Entrance lobby level floor-to-floor height2.0f = 7.8m1.5= 4.65m1.75f = 6.125m
Number of mechanical floors above ground (excluding those on the roof)s/20 = One mechanical floor every 20 storiess/30 = One mechanical floor every 30 storiess/25 = One mechanical floor every 25 stories
Height of mechanical floors2.0f = 7.8m1.5= 4.65m1.75f = 6.125m
Height of roof-level mechanical areas / parapets / screen walls22.0f = 7.8m2.0f = 6.2m2.0f = 7.0m
Key

H= Building height
f = Typical occupied floor-to-floor height
s = Total number of stories3
         
 
Useable Floors
Entrance Lobby
Mechanical Floors
Roof
  
.asdf
1Mixed-use assumptions derived from the average values between office and residential/hotel figures.

2Figures do not assume spires or other major projections at the roof plane.

3The number of stories should include the ground floor level and be the number of main floors above ground, including any significant mezzanine floors and major mechanical plant floors. Mechanical mezzanines or penthouses should not be included if they have a significantly smaller floor area than the major floors below. CTBUH floor counts may differ from published accounts, as it is common in some regions of the world for certain floor levels not to be included (for example, the level 4, 14, 24, etc in Hong Kong).

.
1. Calculating the height of an office tall building where only the number of stories is known
Number of stories (known) = s
Assumed floor-to-floor height = f = 3.9m
Factor for increased ground level floor-to-floor height
Assuming the entrance lobby floor-to-floor height is 7.8m, the factor will be an additional 7.8 minus (–) 3.9 = 3.9m
(e.g. discounting the 3.9m of the ground level floor-to-floor height that has already been counted).
Factor for increased mechanical levels floor-to-floor height
Assuming the mechanical levels are 7.8m high, the factor will be an additional 7.8 minus (–) 3.9 = 3.9m per mechanical floor
(e.g. discounting the 3.9m of the mechanical floors that have already been counted). The number of mechanical floors is calculated by the total number of floors divided by 20 = s/20
Factor for roof level mechanical systems / parapets / roof features
Assume this is an additional 7.8m in height (there is no need to discount any stories as roof level mechanical systems / parapets / roof features are not included in the figure for total story count).

Height of building = number of stories x floor-to-floor height = 3.9s
+ Factor for increased ground level floor-to-floor height = 3.9m
+ Factor for increased mechanical levels floor-to-floor height = 3.9m x (s/20)
+ Factor for roof level mechanical systems / parapets / roof features = 7.8m
Final formula for calculating the height of an office tall building:

.
60 Story Office Building

2. Calculating the height of a residential/hotel tall building where only the number of stories is known
.




Number of stories (known) = s
Assumed floor-to-floor height = f = 3.1m
Factor for increased ground level floor-to-floor height
Assuming the entrance lobby floor-to-floor height is 4.65m, the factor will be an additional 4.65 minus (–) 3.1 = 1.55m
(e.g. discounting the 3.1m of the ground level floor-to-floor height that has already been counted).
Factor for increased mechanical levels floor-to-floor height
Assuming the mechanical levels are 4.65m high, the factor will be an additional 4.65 minus (–) 3.1 = 1.55m per mechanical floor
(e.g. discounting the 3.1m of the mechanical floors that have already been counted). The number of mechanical floors is calculated by the total number of floors divided by 30 = s/30.
Factor for roof level mechanical systems / parapets / roof features
Assume this is an additional 6.2m in height (there is no need to discount any stories as roof level mechanical systems / parapets / roof features are not included in the figure for total story count).

Height of building = number of stories x floor-to-floor height = 3.1s
+ Factor for increased ground level floor-to-floor height = 1.55m
+ Factor for increased mechanical levels floor-to-floor height = 1.55m x (s/30)
+ Factor for roof level mechanical systems / parapets / roof features = 6.2m
Final formula for calculating the height of a residential/hotel building:

.
60 Story Residential/Hotel Building

3. Calculating the height of a mixed-use tall building or where the function of the building is unknown and the number of stories is known
.

Number of stories (known) = s
Assumed floor-to-floor height = f = 3.5m
Factor for increased ground level floor-to-floor height
Assuming the entrance lobby floor-to-floor height is  6.125m, the factor will be an additional  6.125 minus (–) 3.5 = 2.625m
(e.g. discounting the 3.5m of the ground level floor-to-floor height that has already been counted).
Factor for increased mechanical levels floor-to-floor height
Assuming the mechanical levels are  6.125m high, the factor will be an additional 6.125 minus (–) 3.5 = 2.625m per mechanical floor
(e.g. discounting the 3.5m of the mechanical floors that have already been counted). The number of mechanical floors is calculated by the total number of floors divided by 25 = s/25.
Factor for roof level mechanical systems / parapets / roof features
Assume this is an additional 7.0m in height (there is no need to discount any stories as roof level mechanical systems / parapets / roof features are not included in the figure for total story count).

Height of building = number of stories x floor-to-floor height = 3.5s
+ Factor for increased ground level floor-to-floor height = 2.625m
+ Factor for increased mechanical levels floor-to-floor height = 2.625m x (s/25)
+ Factor for roof level mechanical systems / parapets / roof features = 7.0m
Final formula for calculating the height of a mixed-use or function unknown tall building:

.
60 Mixed-Use or Function Unknown Building

Comments

RafaelKlimek said…
Good day! Do you know if they make any plugins to help with SEO? I'm trying to get my blog to rank for some targeted keywords but I'm not seeing very good success. If you know of any please share. Thank you! Alexandr Shcolyar

Popular posts from this blog

Construction Sequence of MEP works in Buildings

Typical Construction Sequence for Mechanical / Electrical / Plumbing Works in High Rise Building Grouping of MEP Fixes like PVC Electrical conduits in Slabs : 1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab) 2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ducting ii) Pressure tests and insulations iii) Installation of FCUs, water heaters (Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix) 3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc. (Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the ceiling tiles - too much coordination is required at

List of Top 200 Construction Companies in the world

The world's 200 largest construction companies Position Company Country 2007 Posit ion Change 1 Vinci France 1 - 2 Bouygues' Construction Divisions France 2 - 3 ACS Spain 5 2 4 Bechtel US 3 -1 5 China Rail way Group China 6 1 6 China Rail way Construction Corporation China 23 17 7 Hochtief Germany 4 -3 8 Ferrovial Spain 11 3 9 China Co mmunications Construction Group China 14 5 10 Skanska Sweden 9 -1 11 FCC Spain 25 14 12 China Stat e Construction & Engineering (CSCEC) China 13 1 13 Eiffage France 21 8 14 Kajima Co rporation Japan 8 -6 15 Fluor US 17 2 16 Strabag S E Austria 22 6 17 Taisei Cor poration Japan 10 -7 18

Tallest Building under construction